Who is waiting for the grid — and who quietly left.

Connection registers list today's queue. When a project is withdrawn or its date slips, the row is edited or simply disappears. We read the queues every day, so each change has a date.

2,220 UK transmission projects1,811 Indian grid applications917 Dutch grid areas✓ read every day
For data-center developers
57 GW
of demand asking to connect to India's interstate grid, across 257 applications — 40 GW still under process. 27 applications are dated in the last 30 days.
CTUIL · counts and megawatts only
For storage and renewables developers
2,220
projects on Britain's transmission register: 1,400 still scoping, 389 built. When one drops out of the queue ahead of you, you see the day.
○ gone, dated · NESO TEC register
For infrastructure funds and analysts
917
Dutch grid areas with a published capacity status, re-read daily. Add 603 GW of generation applications in India, and compare how queues actually move.
● changed, dated
Britain · transmission connection register by project status
StatusProjectsShare
Scoping1,400
Built389
Consents Approved222
Awaiting Consents164
Under Construction/Commissioning45

A register like this shows the queue as of today. What it cannot show is which projects were in it last month and are not now.

India · applications by large loads to connect to the interstate grid
StatusApplicationsDemand
Under Process16439,798 MW
Approved628,566 MW
Closed285,914 MW
Not stated32,615 MW
Daily status changes per application and per project, with the day each one moved, in the full history.Request the full file →

What access gives you

The daily file

Projects that entered a queue, changed status or date, or left it — per register, per day.

The history

Every project since 2026-09-20 with its first-seen day and each change the register made.

A sample first

Real rows for your own question before any contract: name the country or the developer, we send the queue as it stood, day by day.

Ask for the slice you need.

One country, one substation area, one developer — tell us the decision and we send real rows. We reply within two working days.